Capital expenditure in the Exploration and Production segment in 2018–2019 | |||||
Capital expenditure1 on property, plant and equipment made by the PGNiG Group in 2019
|
|
|
Performance vs CAPEX plan
|
||
2019
|
2018
|
2017
|
20192
|
||
|
Exploration and Production, including:
|
2,508
|
2,232
|
1,214
|
58%
|
1
|
Norway
|
1,414
|
1,149
|
275
|
60%
|
2
|
Pakistan
|
136
|
94
|
100
|
55%
|
3
|
Libya
|
4
|
9
|
4
|
48%
|
1) Including capitalised borrowing costs. 2) Based on expenditure incurred and planned in 2017–2019, net of expenditure on acquisition of hydrocarbon deposits in Norway. |
In 2019, PGNiG’s capital expenditure in the Exploration and Production segment amounted to PLN 997m and was in line with the figure reported for 2018. Major investment projects implemented in 2019 included:
PGNiG’s capital expenditure on exploration activities in Poland totalled PLN 594m. Key development projects (in terms of allocated CAPEX) in 2019 included:
PGNiG’s total capital expenditure on foreign production operations reached PLN 147m. This figure includes the capital expenditure made in 2019 in Pakistan, amounting to PLN 136m, up 45% on 2018.
2019 was a record year for PGNiG Upstream Norway in terms of its capital expenditure, which exceeded NOK 3.24bn. Capital expenditure made in 2019 in Norway reached NOK 1.58bn (net of acquisitions). In 2019, the company took steps to maintain production from its existing fields while preserving good operating performance by investing in:
More information on capital expenditure in the Exploration and Production segment in the period 2017-2022 and a detailed description of investments planned and implemented in 2020 is available here.