INVESTMENTS IN 2019

    
 
In 2019, PGNiG TERMIKA was engaged in investment projects which may significantly affect its profit or loss in the coming years. The PGNiG TERMIKA’s and PGNiG TERMIKA EP’s capital expenditure in 2019 totalled approximately PLN 1,628m (including PLN 493m attributable to CO2) and was incurred to upgrade and construct generating units.

One of the key capex projects in 2019 was the construction of a 500 MW CCGT unit at the Żerań CHP plant (Żerań CCGT) Construction work was completed on all main steel and reinforced concrete structures of the key buildings and facilities comprising the CCGT unit, including the gas and steam turbine house, recovery boiler, start-up boiler house and transformer stations. Other works involved construction of auxiliary infrastructure and service lines to gas and electricity transmission networks. In view of the BAT Conclusions, steps were taken to install a catalytic flue gas deNOx (SCR) system. The planned capital expenditure totals approximately PLN 1.6bn. The commissioning of the Żerań CCGT unit, taking into account force majeure (typhoon Jebi in Japan), is expected in November 2020.

In 2019, construction and assembly work at the peak-load boiler house of the Żerań CHP plant, comprising three 130 MWt gas-fired boilers, was completed. In the third quarter of 2019, the unit’s start-up was commenced.

Another project continued in 2019 was the construction of a 450 MW CCGT unit at the Stalowa Wola CHP plant. The work included building and assembly activities performed to finish the construction of the CCGT unit and a back-up heat source, in accordance with the scope of the relevant contracts. Start-up work on the unit’s process systems began. The planned total capital expenditure is approximately PLN 1.4bn; the scheduled commissioning date was postponed to the beginning of Q2 2020.

As part of the Pruszków CHP plant upgrade project, in 2019 the altering of the coal feeding infrastructure and two water boilers, along with the construction of an environmental protection system, was completed. Additionally, work was continued on a detailed concept of and tender documentation for selecting contractors to carry out the investment projects envisaged for 2020-2022, including the construction of two coal-fired boilers, an oil-fired boiler house (with a light oil tank) and gas engines with a total capacity of up to 12 MWe.

Key investment projects at PTEP included:

  • Project related to the supply of heat from own generation sources to the city of Rybnik;
  • Modernisation of the cooling water pump rooms and compressors at the Pniówek Branch;
  • Expansion and upgrade of district heating networks in Jastrzębie-Zdrój.

Capital expenditure at PTEP totalled approximately PLN 57.3m (approximately PLN 34m without CO2) in 2019.

In 2019, PGNiG TERMIKA, via its subsidiary PGNiG TERMIKA Energetyka Rozproszona, took over the operation of the district heating system in Dęblin. Also, processes related to acquisition/district heating investment projects in Przemyśl and Śrem were carried out.

The PGNiG TERMIKA Group is actively involved in innovative programmes. Key R&D projects implemented in 2019 include:

  • Start of work to draft pre-construction documentation for the photovoltaic system project at the Kawęczyn CHP plant;
  • Launch of commercial and technical negotiations with the potential contractor for the project to install pulse duct collectors on boiler No. 7 at the Siekierki CHP plant to reduce dust emissions in the flue gas streams below 10 mg/Nm3.

 

Powrót do góry en

This menu allows you to go to another subpage in this chapter